AIM FOR EXTRAORDINARY

ASI Fiber Group — Aerial Fiber Construction

Fiber in the Air, Built to Last

Aerial fiber optic installation moves fast when it's done right. Here's how ASI Fiber Group approaches every aerial fiber construction project — from the first make-ready assessment to final network handoff.

6
Construction phases from survey to sign-off
99.9%
First call resolution rate
10M+
Feet of fiber placed
01
Phase 01 — Pre-Construction

Route Survey & Pole Assessment

Every aerial fiber construction project starts with a thorough field walk. Our outside plant (OSP) crews assess each pole along the proposed route — documenting existing attachments, available space, structural condition, and clearance to other utilities. This survey tells us exactly what make-ready work is needed before a single foot of cable goes up, and it's the foundation for accurate project scheduling and cost estimates.

Field Survey Pole Inventory Clearance Assessment Make-Ready Scoping OSP Construction
02
Phase 02 — Engineering & Permitting

Pole Loading Analysis & Attachment Agreements

Before any aerial fiber construction work begins on the poles, engineering analysis confirms that each structure can safely carry the added load of a new fiber attachment. Applications are submitted to pole owners — typically electric utilities or municipalities — and all required permits are secured. This phase also covers right-of-way coordination for any road or property crossings. Getting this right up front keeps the project moving without regulatory delays mid-construction.

Structural Loading Pole Attachment Applications ROW Permitting Utility Coordination
03
Phase 03 — Make-Ready Construction

Pole Prep & Hardware Installation

Make-ready is the work required to create space for the new fiber cable on existing poles. This includes transferring or rearranging existing utility attachments, installing new pole hardware such as down-guys, anchors, and brackets, and replacing poles that no longer meet structural requirements. Make-ready is often the longest phase in an aerial project — and the one most directly tied to schedule risk if it isn't scoped carefully from the start.

Transfer of Attachments Down-Guy & Anchor Work Pole Replacement Hardware Installation Broadband Construction
04
Phase 04 — Cable Deployment

Strand Stringing & Fiber Lashing

With poles prepped and permits in hand, crews begin the aerial fiber cable installation by stringing the messenger strand — the steel support wire that carries the weight of the fiber — along the approved route. The fiber cable is then lashed to the strand using a lashing machine that wraps a binding wire in a continuous helix as it travels down the span. For routes where self-supporting cable is specified, ADSS (All-Dielectric Self-Supporting) fiber eliminates the need for a separate strand. Proper sag and tension are set at each span to account for temperature variation and wind loading, protecting the cable over its full service life.

Messenger Strand Cable Lashing Sag & Tension Control Self-Supporting ADSS
05
Phase 05 — Optical Connections

Aerial Splicing & Termination

Individual fiber strands are joined at splice points using fusion splicing, which welds two fiber ends together with a precision electric arc to produce a near-lossless optical connection. For aerial fiber optic installations, splice closures are mounted directly on the strand or at pole locations in weather-hardened enclosures built for long-term outdoor exposure. At service endpoints, cables are terminated with connectors that interface with the active network equipment. Every splice is documented and traceable.

Fusion Splicing Aerial Splice Closures Pole-Mounted Terminals Documentation
06
Phase 06 — Closeout

Testing, As-Builts & Network Handoff

Every installed fiber strand is tested using an Optical Time Domain Reflectometer (OTDR), which identifies splice loss, connector performance, and any faults against project specifications. No aerial fiber optic installation gets handed off without passing full certification. Final as-built documentation is compiled — including pole-by-pole GPS records, splice logs, and attachment diagrams — giving the network owner a complete picture of what was built and where. That record set is the foundation for any future OSP maintenance or expansion work.

OTDR Testing Loss Certification GPS-Referenced As-Builts Owner Handoff Outside Plant
Why It Matters

Aerial fiber optic construction moves faster than underground — but speed without discipline creates problems that are expensive to fix at height. The projects that hold up long-term are the ones where make-ready construction is scoped honestly, strand tension is set correctly, and every splice is tested before the crew moves on. That's the standard ASI Fiber Group holds on every route.